Objects

JSC WA KURGAN

Industry sector: Metallurgy and mechanical engineering

Project: Mounting of the induction furnace at a plant on steel fraction production

Site location: Kurgan

Terms of the work completion on site: July - August, 2009

The description of the performed works: The Reztsoff company executed mounting of the induction furnace of the German company ABP with a productivity rate of 6 t/hour.

It is mounted:

  • 20 tons of the manufactory equipment,
  • 1200 meters of process pipelines.

 

 

Back to object's list